Latest aerial photos of the site.

Latest aerial photos of the site.
Read More


Metal Roofing commenced 27 June 2015 which was contracted to Adams Direct.

Metal Roofing commenced 27 June 2015 which was contracted to Adams Direct. This work is due for completion early next....


Read More

Concrete footpaths installed 25 June 2015 by Slabs R Us these paths are for pedestrian traffic and form part of the emergency exits from building.

Concrete footpaths installed 25 June 2015 by Slabs R Us these paths are for pedestrian traffic and form part of....


Read More

Final coat of Bitumen was installed 19-20 June 2015 for both Car Parks & Access Road, these works were contracted to TRN Group.

Final coat of Bitumen was installed 19-20 June 2015 for both Car Parks & Access Road, these works were contracted....


Read More

Landscaping works commenced on the rear playground on 15 June 2015

Landscaping works commenced on the rear playground on 15 June 2015 for the 3 to 5 area, which is almost....


Read More

Carpark Landscaping works commenced 15 June 2015

Carpark Landscaping works commenced 15 June 2015 and were completed on 19 June 2015, these works were conducted by Sean....


Read More

Timber verandah’s commenced 8 June 2015

Timber verandah's commenced 8 June 2015 and were completed on 12 June 2015, these verandah’s will assist children and staff....


Read More

Concrete verandah’s commenced June 2015

Concrete verandah's commenced June 2015 and were completed the following day, this verandah’s will assist children and staff for the....


Read More

Latest aerial shots of childcare with up to date images of current progress for both building and civil works.

Latest aerial shots of childcare with up to date images of current progress for both building and civil works.
Read More


2 coat bitumen spray seal conducted on access road and north & south carparks as per design.

2 coat bitumen spray seal conducted on access road and north & south carparks as per design. The....


Read More