Latest News

Concrete footpaths constructed in northern carpark.

Concrete footpaths constructed in northern carpark. Concrete works were completed by Slabs R Us. ....


Read More

Brick works commenced 6 May 2015

Brick works commenced 6 May 2015 on the new extension of 7 new classrooms which will consist of brick veneer....


Read More

Timber Roof frame was installed on 18 April 2015

Timber Roof frame was installed over a 3 day period which commenced on 18 April 2015, this involved a team....


Read More

Timber frame, car park lighting installation was completed 25 March 2015.

Timber frame, car park lighting and further concrete carpark kerbing installation was completed 25 March 2015. Southern carpark is the....


Read More

Slab construction was completed on Monday 16 March 2015

Slab construction was completed on Monday 16 March 2015 with the inclusion of partial kerb and gutter for the northern....


Read More

Slab construction and drainage installation has commenced on 27 February 2015

Slab construction and drainage installation has commenced on 27 February 2015, the concrete slab will be poured in 2 stages....


Read More

The eastern roadway commenced 9 February 2015

The eastern roadway commenced 9 February 2015, this will link both the northern and southern Car parks, the roadway will....


Read More

The northern car park works commenced Friday 6 February 2015

The northern car park works commenced Friday 6 February 2015. The car park will consist of 56 single car spaces....


Read More

Earthworks for new road works commenced on 2 February 2015

Earthworks for new road works commenced on 2 February 2015, these works will consist of a dual road being constructed....


Read More

Civil works commenced on 27 January 2015

Civil works commenced on 27 January 2015, these works are being performed by TRN Group. The works consist of road....


Read More