Timber Roof frame was installed on 18 April 2015

Timber Roof frame was installed on 18 April 2015

Timber Roof frame was installed over a 3 day period which commenced on 18 April 2015, this involved a team of highly skilled personnel positioning roof trusses spanning 18.5 meters into position utilising a 35 Tonne Crane which was performing a series of lifts from the northern carpark.

Maurice Sharp Constructions and Pty Ltd with the assistance of Costec Constructions performed the above works with a successful result.

100_2191 100_2197 100_2202 100_2203

Slab construction and drainage installation has commenced on 27 February 2015

Slab construction and drainage installation has commenced on 27 February 2015

Slab construction and drainage installation has commenced on 27 February 2015, the concrete slab will be poured in 2 stages due to the scale of the project. The first pour is scheduled for 13 March 2015 and the second on 17 March 2015 weather permitting. The extension floor area will comprise of 7 new class rooms, bottle prep areas and 3 separate toilet facilities for the children. Overall there are 9 classrooms at the centre.

  • Concrete works performed by Slabs R Us Pty Limited
  • Drainage works performed by Batson Plumbing Pty Limited

100_1882 100_1901 100_1879 100_1855

The northern car park works commenced Friday 6 February 2015

The northern car park works commenced Friday 6 February 2015

The northern car park works commenced Friday 6 February 2015. The car park will consist of 56 single car spaces which will include one way traffic conditions only. In addition the car park has been designed to accommodate disabled parking and selected pedestrian crossings, pathways will also be provided for pedestrians enabling easy access and egress to the child care centre. Furthermore pathways are also designed and will be constructed to accommodate easy access for persons with disabilities.

100_1791 100_1795 100_1799 100_1808

Earthworks for new road works commenced on 2 February 2015

Earthworks for new road works commenced on 2 February 2015

Earthworks for new road works commenced on 2 February 2015, these works will consist of a dual road being constructed from Mandalong Close to the main northern car park, this will be the only point of entry to the child care centre once operational. A series of speed humps and road signage will be positioned throughout the access road and car park areas that will facilitate the vehicular direction of travel.

road1

road2