Final coat of Bitumen was installed 19-20 June 2015 for both Car Parks & Access Road, these works were contracted to TRN Group.
- Landscaping works commenced on the rear playground on 15 June 2015
- Concrete footpaths installed 25 June 2015 by Slabs R Us these paths are for pedestrian traffic and form part of the emergency exits from building.