Timber frame, car park lighting and further concrete carpark kerbing installation was completed 25 March 2015. Southern carpark is the only area remaining to be completed. Timber Roof Trusses will be delivered on 16 April 2015 for installation.
- Slab construction was completed on Monday 16 March 2015
- Timber Roof frame was installed on 18 April 2015