Latest aerial photos of the site.
Latest aerial photos of the site.
![Latest aerial photos of the site. Latest aerial photos of the site.](https://oldmacdonaldschildcare.com.au/wp-content/uploads/2015/08/aerial2-500x300.jpg)
Concrete footpaths installed 25 June 2015 by Slabs R Us these paths are for pedestrian traffic and form part of the emergency exits from building.
Landscaping works commenced on the rear playground on 15 June 2015 for the 3 to 5 area, which is almost complete, these works are being performed by Jamie Miller Landscapes who were highly recommended for constructing childcare play areas. All landscape works are due for completion in August 2015.
Carpark Landscaping works commenced 15 June 2015 and were completed on 19 June 2015, these works were conducted by Sean Keegan of Australian Property Improvements Pty Ltd this company performed their works of a high standard and came recommended.
Timber verandah’s commenced 8 June 2015 and were completed on 12 June 2015, these verandah’s will assist children and staff for the provision of shade and shelter on inclement days.